HJ Shipbuilding files ₩60.1bn Ulsan plant decommissioning contract

HJ Shipbuilding & Construction · KOSPI · 097230 · Nov 11, 2026 · Supply contracts

HJ Shipbuilding & Construction filed a supply contract worth ₩60.1bn with Korea East-West Power Co., Ltd. for decommissioning work at the Ulsan Power Plant. The contract period runs from Feb 15, 2024 to May 29, 2027, and the amount is 3.4% of revenue as reported.

Key facts

Contract nameUlsan Power Plant Units 4,5,6 Decommissioning Work (Comprehensive Screening Bid System)
CounterpartyKorea East-West Power Co., Ltd.
Contract amount₩60.1bn
% of revenue (as reported)3.4%
Period startFeb 15, 2024
Period endMay 29, 2027

Comparison

Amount as % of FY2025 revenue (calculated)3.0%
Revenue 2025₩2.0tn
Revenue 2024₩1.9tn
Revenue 2023₩2.2tn

Context

In the 12 months before this filing, the company filed 23 supply contracts totaling ₩4.0tn. By our calculation, this contract equals 3.0% of FY2025 revenue.

Key metrics

Supply contracts

Supply contracts, last 12 months₩4.0tn As of Nov 10, 2026 Source 1 ↗, Source 2 ↗, Source 3 ↗, Source 4 ↗, Source 5 ↗ +18 more
Supply contracts vs prior-year revenue198.5% As of Nov 10, 2026 Source 1 ↗, Source 2 ↗, Source 3 ↗, Source 4 ↗, Source 5 ↗ +18 more
Contracts without a KRW amount0 contracts without a KRW amount excluded As of Nov 19, 2026